[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93515":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93515,64,1,"单选题","盈亏平衡点生产负荷率与项目抗风险能力的关系是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","两者无关",false,{"key":16,"text":17,"correct":14},"B","盈亏平衡点生产负荷率越大，则抗风险能力越强",{"key":19,"text":20,"correct":21},"C","盈亏平衡点生产负荷率越小，则抗风险能力越强",true,{"key":23,"text":24,"correct":14},"D","盈亏平衡点生产符合率大于50％，则项目风险可接受","本题考查的是盈亏平衡点生产负荷率的大小与风险的关系。生产负荷率越小，则承担的风险越小，抗风险能力越强。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]