[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93505":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93505,64,1,"单选题","以下不是价值工程分析阶段的工作内容的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","功能成本分析",false,{"key":16,"text":17,"correct":14},"B","功能评价",{"key":19,"text":20,"correct":21},"C","工作对象选择",true,{"key":23,"text":24,"correct":14},"D","功能定义","此题考查价值工程工作阶段的内容。价值工程在分析阶段的工作内容有功能定义、功能整理、功能成本分析、功能评价、确定改进范围。工作对象选择属于准备阶段的工作内容。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]