[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93504":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93504,64,1,"单选题","下列关于盈亏平衡点的生产负荷率与建设项目风险随能力的关系，说法不正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","生产负荷率越小，则风险越小",false,{"key":16,"text":17,"correct":18},"B","生产负荷率越小，即承受风险的能力越差",true,{"key":20,"text":21,"correct":14},"C","生产负荷率越大，则风险越大",{"key":23,"text":24,"correct":14},"D","生产负荷率越小，可以承受较大的风险","本题考查的是盈亏平衡分析。 生产负荷率是衡量建设项目生产负荷状况的重要指标。该值越小，则风险越小，即可以承受较大的风险；该值越大，则风险越大，即承受风险的能力越差。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]