[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93486":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93486,64,1,"单选题","盈亏平衡点的生产负荷率与建设项目风险承受能力的关系是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","盈亏平衡点的生产负荷率的大小与项目风险无关",false,{"key":16,"text":17,"correct":18},"B","盈亏平衡点的生产负荷率越大，风险越大",true,{"key":20,"text":21,"correct":14},"C","盈亏平衡点的生产负荷率越小，风险越大",{"key":23,"text":24,"correct":14},"D","盈亏平衡点的生产负荷率能揭示产生项目风险的根源","此题考查生产负荷率与项目风险的关系。生产负荷率是衡量项目生产负荷状况的重要指标。该值越小，则风险越小，说明项目可承受较大的风险；该值越大，则风险越大，项目所承受风险的能力就越差。盈亏平衡分析虽然能够度量项目风险大小，但并不能揭示产生项目风险的根源。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]