[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93481":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93481,64,1,"单选题","如果某常规投资项目的净现值为负数，则必然存在的结论是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投资回收期在1年之内",false,{"key":16,"text":17,"correct":14},"B","投资回收期小于基准投资回收期",{"key":19,"text":20,"correct":21},"C","内部收益率小于基准收益率",true,{"key":23,"text":24,"correct":14},"D","年均现金流量大于原始投资","此题考查对经济评价指标的理解。投资方案的净现值为负数，说明该投资项目未能达到预定的收益率水平，应考虑拒绝该项目。由投资回收期的判别准则得出，该项目投资回收期大于基准投资回收期，故选项B错误。由常规项目的净现值NPV与内部收益率IRR的关系图(见下图)可知，净现值NPV",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]