[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93471":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93471,64,1,"单选题","某建设项目的现金流量为常规现金流量，当基准收益率为8％时，净现值为400万元。若基准收益率变为10％，该项目的NPV( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","大于400万元",false,{"key":16,"text":17,"correct":18},"B","小于400万元",true,{"key":20,"text":21,"correct":14},"C","等于400万元",{"key":23,"text":24,"correct":14},"D","不确定","此题考查净现值与基准收益率的关系。对于常规型投资项目，在其定义域-1\u003Ci\u003C∞区间，净现值是一条单调递降的曲线，净现值会随i的增大而减小。故当基准收益率由8％变为10％时，净现值会减小，即小于400万元。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]