[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93469":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93469,64,1,"单选题","下列关于投资回收期的描述，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","同一项目，动态投资回收期要比静态投资回收期更长些",true,{"key":16,"text":17,"correct":18},"B","投资回收期是一个动态指标",false,{"key":20,"text":21,"correct":18},"C","投资回收期是一个静态指标",{"key":23,"text":24,"correct":18},"D","投资回收期从项目开始投入之日算起，到项目结束为止","此题考查对投资回收期的理解。投资回收期按是否考虑资金时间价值分为静态投资回收期(静态指标)和动态投资回收期(动态指标)；对于同一项目，考虑资金时间价值计算出的动态投资回收期要比静态投资回收期更长些；投资回收期一般从项目建设起始年算起，也可从项目投产年算起，计算时注明即可。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]