[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93434":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93434,64,1,"单选题","对于政府投资项目，初步设计投资概算超过经批准的可行性研究报告中投资估算（ ）的，项目单位应当向投资主管部门或者其他有关部门报告。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5%",false,{"key":16,"text":17,"correct":14},"B","8%",{"key":19,"text":20,"correct":21},"C","10%",true,{"key":23,"text":24,"correct":14},"D","12%","工程设计工作一般划分为两个阶段，即初步设计和施工图设计。对于政府投资项目，初步设计提出的投资概算超过经批准的可行性研究报告提出的投资估算10%的，项目单位应当向投资主管部门或者其他有关部门报告，投资主管部门或者其他有关部门可以要求项目单位重新报送可行性研究报告。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]