[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93411":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93411,64,1,"单选题","需审批建设用地的建设项目应在( )阶段，由建设用地单位提出申请。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目申请书",false,{"key":16,"text":17,"correct":18},"B","可行性研究",true,{"key":20,"text":21,"correct":14},"C","初步设计",{"key":23,"text":24,"correct":14},"D","开发建设","此题考查建设用地申请。需审批的建设项目在可行性研究阶段，由建设用地单位提出申请；需核准的建设项目在项目申请报告核准前，由建设单位提出申请；需备案的建设项目在办理备案手续后，由建设单位提出申请。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]