[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93407":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93407,64,1,"单选题","下列关于房地产开发企业在项目施工阶段中进行的施工管理的内容表述错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","所有隐蔽工程验收记录必须经项目监理机构等有关验收单位签字认可后，方可组织下道工序施工",false,{"key":16,"text":17,"correct":14},"B","施工阶段投资控制的关键是对工程变更、签证实行有效控制",{"key":19,"text":20,"correct":21},"C","监理单位要对施工索赔做到事前把关、主动监控，严格审核工程变更，计算各项变更对总投资的影响",true,{"key":23,"text":24,"correct":14},"D","建设单位管理人员对施工进度的检查与进度计划的贯彻实施是融汇在一起的","建设单位要对施工索赔做到事前把关、主动监控，严格审核工程变更，计算各项变更对总投资的影响；对施工单位及材料供应商不履行约定义务及时提出反索赔，使投资得到有效控制，故C错误。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]