[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93393":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93393,64,1,"单选题","在项目审批制度上，政府仅对重大项目和限制类项目从维护社会公共利益角度进行()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","备案",false,{"key":16,"text":17,"correct":18},"B","核准",true,{"key":20,"text":21,"correct":14},"C","审批",{"key":23,"text":24,"correct":14},"D","规范","此题考查投资决策阶段，政府投资项目的审批。政府采取直接投资、资本金注入方式投资的项目，政府部门需要严格审批项目建议书、可行性研究报告、初步设计和概算；对于采用投资补助、贷款贴息等方式的政府投资项目，政府部门只审批资金申请报告。非政府投资建设的项目，一律不再实行审批制，区别不同情况实行核准制或备案制。其中，政府仅对重大项目和限制类项目从维护社会公共利益角度进行核准，其他项目无论规模大小，均改为备案制。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]