[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93352":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},93352,64,1,"单选题","发包人未经竣工验收擅自使用工程的，其竣工日期应自（ ）之日起算。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","补充进行竣工验收",false,{"key":16,"text":17,"correct":14},"B","承包人交付",{"key":19,"text":20,"correct":14},"C","发包人正式使用",{"key":22,"text":23,"correct":24},"D","转移占有",true,"当事人对建设工程实际竣工日期有争议的，按照以下情形分别处理：①建设工程经竣工验收合格的，以竣工验收合格之日为竣工日期；②承包人已经提交竣工验收报告，发包人拖延验收的，以承包人提交验收报告之日为竣工日期；③建设工程未经竣工验收，发包人擅自使用的，以转移占有建设工程之日为竣工日期。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]