[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93350":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93350,64,1,"单选题","隐蔽工程经重新检验证明工程质量符合合同要求，由此增加的费用应当由（ ）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理人",false,{"key":16,"text":17,"correct":18},"B","发包人",true,{"key":20,"text":21,"correct":14},"C","承包人",{"key":23,"text":24,"correct":14},"D","设计人","经监理人检查质量合格或监理人未按约定的时间进行检查的，承包人覆盖工程隐蔽部位后，监理人对质量有疑问的，可要求承包人对已覆盖的部位进行钻孔探测或揭开重新检验。经检验证明工程质量符合合同要求的，由发包人承担由此增加的费用和（或）工期延误，并支付承包人合理利润；经检验证明工程质量不符合合同要求的，由此增加的费用和（或）工期延误由承包人承担。承包人为通知监理人到场检查，私自将工程隐蔽部位覆盖的，监理人有权指示承包人钻孔探测或揭开检查，由此增加的费用和（或）工期延误由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]