[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93348":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},93348,64,1,"单选题","承包人应在知道或应当知道索赔事件发生后28天内，向监理人递交（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","索赔报告",false,{"key":16,"text":17,"correct":14},"B","索赔档案",{"key":19,"text":20,"correct":14},"C","正式的索赔通知书",{"key":22,"text":23,"correct":24},"D","索赔意向通知书",true,"承包人根据合同认为有权得到追加付款和（或）延长工期时，应按规定程序向发包人提出索赔。承包人应在知道或应当知道索赔事件发生后28天内，向监理人递交索赔意向通知书，并说明发生索赔事件的事由。承包人应在发出索赔意向通知书后28天内，向监理人递交正式的索赔通知书，详细说明索赔理由以及要求追加的付款金额和（或）延长的工期，并附必要的记录和证明材料。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]