[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93346":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93346,64,1,"单选题","除专用合同条款另有约定外，经验收合格的工程实际竣工日期，以（ ）为准。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理人对承包人提交的竣工验收申请报告表示同意的日期",false,{"key":16,"text":17,"correct":14},"B","发包人验收同意接收工程的日期",{"key":19,"text":20,"correct":21},"C","承包人提交竣工验收申请报告的日期",true,{"key":23,"text":24,"correct":14},"D","工程验收合格后发包人与承包人商定的日期","竣工验收合格的，监理人应在收到竣工验收申请报告后的56天内，向承包人出具经发包人签认的工程接收证书。实际竣工日期为承包人提交竣工验收申请报告的日期，并应在工程接收证书中写明。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]