[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93344":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93344,64,1,"单选题","工程勘察合同履行中，勘察服务期限自（ ）起计算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实际勘察日期",false,{"key":16,"text":17,"correct":14},"B","发包人支付定金",{"key":19,"text":20,"correct":21},"C","开始勘察通知中载明的开始勘察日期",true,{"key":23,"text":24,"correct":14},"D","提交勘察服务资料","根据发包人主要义务，符合专用合同条款约定的开始勘察条件的，发包人应提前7天向勘察人发出开始勘察通知。勘察服务期限自开始勘察通知中载明的开始勘察日期起计算。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]