[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93339":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93339,64,1,"单选题","工程设计合同履行过程中，设计人发生违约情况时，下列说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人可向设计人发出整改通知",false,{"key":16,"text":17,"correct":14},"B","设计人逾期仍不纠正的，发包人有权解除合同并向设计人发出解除合同通知",{"key":19,"text":20,"correct":21},"C","设计人逾期仍不纠正的，发包人不能解除合同",true,{"key":23,"text":24,"correct":14},"D","设计人应当承担由于违约所造成的费用增加","A项，设计人发生违约情况时，发包人可向设计人发出整改通知，要求其在限定期限内纠正；BC两项，逾期仍不纠正的，发包人有权解除合同并向设计人发出解除合同通知。D项，设计人应当承担由于违约所造成的费用增加、周期延误和发包人损失等。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]