[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93338":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93338,64,1,"单选题","工程设计合同履行中，设计服务期限自( )起计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","开始设计通知中载明的开始设计日期",true,{"key":16,"text":17,"correct":18},"B","实际开始设计日期",false,{"key":20,"text":21,"correct":18},"C","设计合同签订日",{"key":23,"text":24,"correct":18},"D","提交设计资料之日","此题考查工程设计合同履行过程中发包人主要义务。符合专用合同条款约定的开始设计条件的，发包人应提前7天向设计人发出开始设计通知。设计服务期限自开始设计通知中载明的开始设计日期起计算。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]