[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93337":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93337,64,1,"单选题","关于对承包人索赔文件审核的说法，正确的是( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理人收到承包人提交的索赔通知书后，应及时转交发包人，监理人无权要求承包人提交原始记录",false,{"key":16,"text":17,"correct":18},"B","承包人接受索赔处理结果的，发包人应在作出索赔处理结果答复后28天内完成赔付",true,{"key":20,"text":21,"correct":14},"C","监理人根据发包人的授权，在收到索赔通知书的60天内，将索赔处理结果答复承包人",{"key":23,"text":24,"correct":14},"D","承包人不接受索赔处理结果的，应直接向法院起诉索赔","此题考查承包人索赔相关内容。监理人收到承包人提交的索赔通知书后，应及时审查索赔通知书的内容、查验承包人的记录和证明材料，必要时监理人可要求承包人提交全部原始记录副本。监理人应在收到索赔通知书或有关索赔的进一步证明材料后的42天内，将索赔处理结果答复承包人。承包人接受索赔处理结果，发包人应在作出索赔处理结果答复后28天内完成赔付。承包人不接受索赔处理结果的，按合同争议解决。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]