[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93333":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93333,64,1,"单选题","按《建设工程施工合同(示范文本)》(GF-2017-0201)的约定，工程师在收到承包人送交的索赔报告和有关资料后，应于（）天内给予答复，或要求承包人进一步补充索赔理由和证据。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","28",true,{"key":16,"text":17,"correct":18},"B","21",false,{"key":20,"text":21,"correct":18},"C","14",{"key":23,"text":24,"correct":18},"D","7","工程师在收到承包人送交的索赔报告和有关资料后，应于28天内给予答复，或要求承包人进一步补充索赔理由和证据，否则视为该项索赔已经认可。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]