[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93329":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93329,64,1,"单选题","那些使实际情况与合同规定不符合，最终引起工期和费用变化的事件，称为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","干扰事件",true,{"key":16,"text":17,"correct":18},"B","顺延事件",false,{"key":20,"text":21,"correct":18},"C","延误事件",{"key":23,"text":24,"correct":18},"D","工程合同","索赔事件，又称干扰事件，是指那些使实际情况与合同规定不符合，最终引起公期和费用变化的事件。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]