[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93323":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93323,64,1,"单选题","发包人和承包人就具体工程项目的建筑施工、设备安装、设备调试、工程保修等工作内容，明确双方权利、义务关系的协议称为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设工程勘察合同",false,{"key":16,"text":17,"correct":14},"B","建设工程设计合同",{"key":19,"text":20,"correct":21},"C","建设工程施工合同",true,{"key":23,"text":24,"correct":14},"D","建设工程监理合同","此题考查的是建筑工程施工合同的概念。建设工程施工合同是指发包人和承包人就具体工程项目的建筑施工、设备安装、设备调试、工程保修等工作内容，明确双方权利、义务关系的协议。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]