[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93300":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93300,64,1,"单选题","下列关于索赔处理的说法中，不正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","当工程师确定的索赔额超过其权限范围时，必须报请发包人批准",false,{"key":16,"text":17,"correct":14},"B","通常工程师对索赔的处理决定不是终局的，对发包人和承包人都不具有强制的约束力",{"key":19,"text":20,"correct":21},"C","承包人如果不同意最终的索赔处理决定．诉讼解决是最理想的方式",true,{"key":23,"text":24,"correct":14},"D","工程师在收到承包人递交的有关资料后28天内未予答复或未对承包人作出进一步要求的，视为该索赔已经认可","如果承包人不接受最终的索赔处理决定，通过协商双方达到互谅互让的解决方案，是处理争议最理想的方式。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]