[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93282":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},93282,64,1,"单选题","设计施工总承包合同，合同文件解释顺序说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同文件解释顺序第一位是中标通知书",false,{"key":16,"text":17,"correct":14},"B","合同文件解释顺序第一位是发包人要求",{"key":19,"text":20,"correct":14},"C","合同文件解释顺序第一位是投标函及投标函附录",{"key":22,"text":23,"correct":24},"D","如有不明确或不一致之处，以合同约定次序在先者为准",true,"合同协议书与下列文件一起构成合同文件:①中标通知书；②投标函及投标函附录；③专用合同条款;④通用合同条款;⑤发包人要求；⑥价格清单;⑦承包人建议;⑧其他合同文件。上述文件互相补充和解释，如有不明确或不一致之处，以合同约定次序在先者为准。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]