[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93274":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93274,64,1,"单选题","下列关于建设工程实际竣工日期有争议的情形，处理正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设工程经竣工验收合格的,以承包人提交验收报告之日为竣工日期",false,{"key":16,"text":17,"correct":18},"B","承包人已经提交竣工验收报告，发包人拖延验收的,以承包人提交验收报告之日为竣工日期",true,{"key":20,"text":21,"correct":14},"C","建设工程未经竣工验收，发包人擅自使用的，以竣工验收合格之日为竣工日期",{"key":23,"text":24,"correct":14},"D","建设工程未经竣工验收，发包人擅自使用的，以承包人提交验收报告之日为竣工日期","当事人对建设工程实际竣工日期有争议的，按照以下情形分别处理:建设工程经竣工验收合格的,以竣工验收合格之日为竣工日期；承包人已经提交竣工验收报告，发包人拖延验收的,以承包人提交验收报告之日为竣工日期；建设工程未经竣工验收，发包人擅自使用的，以转移占有建设工程之日为竣工日期。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]