[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93266":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93266,64,1,"单选题","某工程施工过程中，承包人未通知监理人检查，私自对某隐蔽部位进行了覆盖，监理人指示承包人揭开检查，经检查该隐蔽部位质量符合合同要求。根据《标准施工招标文件》，由此增加的费用和（或）工期延误应由（ ）承担。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":14},"B","监理人",{"key":19,"text":20,"correct":21},"C","承包人",true,{"key":23,"text":24,"correct":14},"D","分包人","承包人未通知监理人到场检查，私自将工程隐蔽部位覆盖的，监理人有权指示承包人钻孔探测或揭开检查，由此增加的费用和（或）工期延误由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]