[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93258":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93258,64,1,"单选题","监理人收到承包人的书面建议后,应与发包人共同研究，确认存在变更的，应在收到承包 人书面建议后的（ ）天内作出变更指示。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","28",{"key":23,"text":24,"correct":14},"D","30","监理人收到承包人的书面建议后,应与发包人共同研究，确认存在变更的，应在收到承包 人书面建议后的14天内作出变更指示。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]