[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93255":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93255,64,1,"单选题","发包人在收到承包人竣工验收申请报告56天后未进行验收，则确定承包人的实际竣工日期应是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人提交竣工验收申请报告日",true,{"key":16,"text":17,"correct":18},"B","发包人组织竣工验收日",false,{"key":20,"text":21,"correct":18},"C","开始进行竣工检验日",{"key":23,"text":24,"correct":18},"D","验收组通过竣工验收日","此题考查实际竣工日期。发包人在收到承包人竣工验收申请报告56天后未进行验收，视为验收合格。实际竣工日期以提交竣工验收申请报告的日期为准,但发包人由于不可抗力不能进行验收的情况除外。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]