[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93237":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93237,64,1,"单选题","《标准施工招标文件》（2007年版）中合同条款规定，发包人提供的材料和工程设备不符合合同要求时，承包人可获得的补偿内容是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工期+利润",false,{"key":16,"text":17,"correct":14},"B","工期+费用",{"key":19,"text":20,"correct":21},"C","工期+费用+利润",true,{"key":23,"text":24,"correct":14},"D","费用+利润","此题考查工程施工阶段承包人索赔。根据《标准施工招标文件》中的合同条款，承包人索赔原因及可补偿内容可知，因发包人提供的材料和工程设备不符合合同要求，承包人可索赔工期、费用和利润。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]