[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93235":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93235,64,1,"单选题","已标价工程量清单中无适用或类似子目的单价，可按照( )的原则，由发、承包双方商定或确定变更工作的单价。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本加税金",false,{"key":16,"text":17,"correct":18},"B","成本加利润",true,{"key":20,"text":21,"correct":14},"C","成本加管理费用",{"key":23,"text":24,"correct":14},"D","制造费用加管理费用","此题考查工程施工阶段变更估价的原则。变更估价原则：①已标价工程量清单中有适用于变更工作的子目，采用该子目的单价计算变更费用；②已标价工程量清单中无适用于变更工作的子目，但有类似子目，可在合理范围内参照类似子目的单价，由监理人商定或确定变更工作的单价；③已标价工程量清单中无适用或类似子目的单价，可按照成本加利润的原则，由监理人商定或确定变更工作的单价。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]