[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93233":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93233,64,1,"单选题","由发包人责任引起的暂停施工造成工期延误的，承包人有权要求发包人()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","延长工期和增加费用，但不支付利润",false,{"key":16,"text":17,"correct":18},"B","延长工期和（或）增加费用，并支付合理利润",true,{"key":20,"text":21,"correct":14},"C","延长工期和（或）支付合理利润，但不增加费用",{"key":23,"text":24,"correct":14},"D","增加费用和支付合理利润，但不延长工期","此题考查工程施工阶段进度管理相关内容。由承包人责任引起的暂停施工，增加的费用和工期由承包人承担；由发包人责任引起的暂停施工，承包人有权要求发包人延长工期和（或）增加费用，并支付合理利润。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]