[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93232":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93232,64,1,"单选题","根据《标准施工招标文件》（2007年版），对于发包人提供的材料和工程设备，承包人应在约定时间内()共同进行验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","会同监理人在交货地点",true,{"key":16,"text":17,"correct":18},"B","会同发包人代表、监理人在交货地点",false,{"key":20,"text":21,"correct":18},"C","会同监理人在施工现场",{"key":23,"text":24,"correct":18},"D","会同发包人代表、监理人在施工现场","此题考查工程施工阶段质量合同管理相关内容。对于发包人提供的材料和工程设备，承包人应根据合同进度计划的安排，向监理人报送要求发包人交货的日期计划。发包人应按照监理人与合同双方当事人商定的交货日期，向承包人提交材料和工程设备，并在到货7天前通知承包人。承包人会同监理人在约定的时间内，在交货地点共同进行验收。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]