[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93231":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93231,64,1,"单选题","下列有关发包人提供材料和工程设备的描述，错误的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人应根据合同进度计划的安排，向监理人报送要求发包人交货的日期计划",false,{"key":16,"text":17,"correct":14},"B","发包人应在材料和工程设备到货7天前通知承包人",{"key":19,"text":20,"correct":21},"C","发包人提供的材料和工程设备运至交货地点验收后，由监理人负责接收、卸货",true,{"key":23,"text":24,"correct":14},"D","承包人会同监理人在约定的时间内，在交货地点共同进行验收","此题考查工程施工阶段质量合同管理相关内容。对于发包人提供的材料和工程设备，承包人应根据合同进度计划的安排，向监理人报送要求发包人交货的日期计划。发包人应按照监理人与合同双方当事人商定的交货日期，向承包人提交材料和工程设备，并在到货7天前通知承包人。承包人会同监理人在约定的时间内，在交货地点共同进行验收。发包人提供的材料和工程设备验收后，由承包人负责接收、保管和施工现场内的二次搬运所发生的费用。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]