[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93229":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93229,64,1,"单选题","工程施工准备阶段，( )负责修建、维修、养护和管理施工所需的临时道路。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包单位",false,{"key":16,"text":17,"correct":18},"B","承包单位",true,{"key":20,"text":21,"correct":14},"C","监理单位",{"key":23,"text":24,"correct":14},"D","设计单位","此题考查施工准备阶段承包人主要义务。工程施工准备阶段，承包人应负责修建、维修、养护和管理施工所需的临时道路，以及为开始施工所需的临时工程和必要的设施，满足开工要求。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]