[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93225":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93225,64,1,"单选题","发包人应在监理人收到( )后28天内，将进度应付款支付给承包人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度付款申请单",true,{"key":16,"text":17,"correct":18},"B","预付款保函",false,{"key":20,"text":21,"correct":18},"C","责任保修单",{"key":23,"text":24,"correct":18},"D","竣工付款申请单","此题考查施工阶段工程款支付管理相关内容。发包人应在监理人收到进度付款申请单后的28天内，将进度应付款支付给承包人。发包人不按期支付，按专用合同条款的约定支付逾期付款违约金。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]