[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93222":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93222,64,1,"单选题","设计人更换项目负责人应事先征得发包人同意，并应在更换（ ）天前将拟更换的项目负责人的姓名和详细资料提交发包人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","21",{"key":23,"text":24,"correct":14},"D","28","设计人更换项目负责人应事先征得发包人同意，并应在更换14天前将拟更换的项目负责人的姓名和详细资料提交发包人。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]