[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93221":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93221,64,1,"单选题","工程勘察合同履行过程中，主要勘察人员应相对稳定，更换主要勘察人员的，应取得( )的同意。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","勘察单位负责人",false,{"key":16,"text":17,"correct":18},"B","发包人",true,{"key":20,"text":21,"correct":14},"C","专业监理工程师",{"key":23,"text":24,"correct":14},"D","总监理工程师","此题考查勘察人主要义务。勘察人应在接到开始勘察通知之日起7天内，向发包人提交勘察项目机构以及人员安排的报告，其内容应包括项目机构设置、主要勘察人员和作业人员的名单及资格条件。主要勘察人员应相对稳定，更换主要勘察人员的，应取得发包人的同意，并向发包人提交继任人员的资格、管理经验等资料。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]