[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93219":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93219,64,1,"单选题","除专用合同条款另有约定外，发包人对于设计文件的审查期限，自文件接收之日起不应超过( )天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","12",{"key":19,"text":20,"correct":21},"C","14",true,{"key":23,"text":24,"correct":14},"D","28","此题考查工程设计合同履行中发包人主要义务。除专用合同条款另有约定外，发包人对于设计文件的审查期限，自文件接收之日起不应超过14天。发包人逾期未作出审查结论且未提出异议的，视为设计人的设计文件已通过发包人审查。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]