[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93209":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93209,64,1,"单选题","英国NEC工程施工合同文本结构中主要选项条款中，选项C对应( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","带有分项工程表的目标合同",true,{"key":16,"text":17,"correct":18},"B","带有分项工程表的标价合同",false,{"key":20,"text":21,"correct":18},"C","带有工程量清单的标价合同",{"key":23,"text":24,"correct":18},"D","带有工程量清单的目标合同","此题考查英国NEC工程施工合同文本结构中主要选项条款。主要选项条款是对核心条款的补充和细化，每一主要选项条款均有许多针对核心条款的补充规定，只要将对应序号的补充条款纳入核心条款即可。主要选项条款包括：选项A：带有分项工程表的标价合同；选项B：带有工程量清单的标价合同；选项C：带有分项工程表的目标合同；选项D：带有工程量清单的目标合同；选项E：成本补偿合同；选项F：管理合同。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]