[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93191":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},93191,64,1,"单选题","下列关于环境影响评价相关要求的说法，错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","环境影响评价文件中的环境影响报告书，应当由具有相应环境影响评价资质的机构编制",false,{"key":16,"text":17,"correct":14},"B","建设单位报批的环境影响报告书应当附具对有关单位、专家和公众的意见采纳或者不采纳的说明",{"key":19,"text":20,"correct":14},"C","建设项目环境影响报告书经批准后，建设项目的性质发生重大变动的，建设单位应当重新报批建设项目环境影响报告书",{"key":22,"text":23,"correct":24},"D","建设项目环境影响报告书自批准之日起满3年，建设项目方开工建设的，其环境影响报告书应当报原审批部门重新审核",true,"环境影响评价是指对规划和建设项目实施后可能造成的环境影响进行分析、预测和评估，提出预防或者减轻不良环境影响的对策和措施，进而跟踪监测的方法和制度。D项，建设项目环境影响报告书、环境影响报告表自批准之日起满5年，建设项目方开工建设的，其环境影响报告书、环境影响报告表应当报原审批部门重新审核。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]