[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93188,64,1,"单选题","在对投资项目进行敏感性分析时，临界点是指不确定因素的变化使项目（）的临界数值。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由可行变为不可行",true,{"key":16,"text":17,"correct":18},"B","由低风险变为高风险",false,{"key":20,"text":21,"correct":18},"C","由敏感性弱变为敏感性强",{"key":23,"text":24,"correct":18},"D","由盈利变为不盈利","临界点是指不确定因素的变化使项目由可行变为不可行的临界数值。此题考查敏感性分析临界点的含义。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]