[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93121":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},93121,64,1,"单选题","在进行建设项目国民经济评价时，采用的折现率是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","行业折现率",false,{"key":16,"text":17,"correct":14},"B","外部收益率",{"key":19,"text":20,"correct":14},"C","资金成本率",{"key":22,"text":23,"correct":24},"D","社会折现率",true,"此题考查国民经济评价与财务评价的联系。国民经济评价是从国家整体角度考察项目效益和费用，采用的是影子价格、影子工资、影子汇率和社会折现率等，计算项目给国民经济带来的净效益，评价项目经济上的合理性。国民经济评价可以在财务评价的基础上进行，也可以直接进行。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]