[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93114":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},93114,64,1,"单选题","在工程项目投资决策阶段进行的总体性策划活动指的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程项目构思策划",true,{"key":16,"text":17,"correct":18},"B","工程项目设计策划",false,{"key":20,"text":21,"correct":18},"C","工程项目初步策划",{"key":23,"text":24,"correct":18},"D","工程项目实施策划","工程项目构思策划是指在工程项目投资决策阶段进行的总体性策划活动,通过确立项目目标、定义项目功能、估算项目投资和建设周期、开展技术经济论证，以确保整个项目建立在可靠 、坚实 、优化的基础之上。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]