[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93089":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93089,64,1,"单选题","某工程6月份已完成工程量金额为5000万元，合同中约定采用价格指数调整法进行合同价款调整。已知定值权重为0.25。可调因子有三项，权重分别为0.15、0.35和0.25。6月份价格指数比基准日期分别增长了15%、20%和25%。则6月份工程价款调整金额是（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","662",false,{"key":16,"text":17,"correct":14},"B","750",{"key":19,"text":20,"correct":21},"C","775",true,{"key":23,"text":24,"correct":14},"D","1000","价格指数调整法是因人工、材料和工程设备、施工机械台班等价格波动影响合同价格时，应按下式计算差额并调整合同价款： 本题中，6月份工程价款调整金额＝5000×〔0.25＋（0.15×1.15＋0.35×1.20＋0.25×1.25）－1〕＝775（万元）。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]