[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93087":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93087,64,1,"单选题","在合同价款结算过程中，发承包双方要根据合同约定进行工程计量。关于工程计量的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","若发现招标工程量清单中出现工程量偏差，发包人不予计量",false,{"key":16,"text":17,"correct":14},"B","工程计量应在承包人提交竣工结算文件之后进行",{"key":19,"text":20,"correct":21},"C","因承包人原因造成超出合同工程范围施工的工程量，发包人不予计量",true,{"key":23,"text":24,"correct":14},"D","进行工程计量后，由发包人提交当期已完工程量报告","工程计量是发承包双方根据合同约定，对承包人完成合同工程的数量进行的计算和确认。正确进行工程计量是工程价款支付的前提。在工程计量中，工程量必须按照相关工程现行国家计量规范规定的工程量计算规则计算。工程计量可选择按月或按工程形象进度分段计量，具体计量周期应在合同中约定。因承包人原因造成的超出合同工程范围施工或返工的工程量，发包人不予计量。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]