[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93086":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},93086,64,1,"单选题","工程预付款的扣回方式是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","以索赔方式扣回",false,{"key":16,"text":17,"correct":14},"B","在竣工结算后协商扣回",{"key":19,"text":20,"correct":14},"C","在开工后28天内以抵冲进度款的方式一次性扣回",{"key":22,"text":23,"correct":24},"D","以抵冲各期工程进度款的方式陆续扣回",true,"在施工过程中，应按照合同条款中约定的时间、数额和比例，将已支付的预付款以抵充各期工程进度款的方式陆续扣回，直到扣回的金额达到合同约定的预付款金额为止。通常约定，承包人完成合同价款的比例在20%～30%时，开始从进度款中按一定比例扣还工程预付款。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]