[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93085":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},93085,64,1,"单选题","某工程合同履行期间，工程量清单项目的工程量增加25%。关于该工程价款调整原则的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","应将该清单项目全部工程量的综合单价予以调高",false,{"key":16,"text":17,"correct":14},"B","应将该清单项目部分增加的工程量的综合单价予以调高",{"key":19,"text":20,"correct":14},"C","应将该清单项目全部工程量的综合单价予以调低",{"key":22,"text":23,"correct":24},"D","应将该清单项目部分增加的工程量的综合单价予以调低",true,"合同履行期间如出现工程量偏差，发承包双方应调整合同价款。当工程量增加15%以上时，其增加部分的工程量综合单价应予调低；当工程量减少15%以上时，减少后剩余部分的工程量综合单价应予调高。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]