[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93084":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93084,64,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500—2013），招标工程合同价款调整的基准日是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标文件发布前28天",false,{"key":16,"text":17,"correct":18},"B","投标截止日前28天",true,{"key":20,"text":21,"correct":14},"C","招标文件发布后28天",{"key":23,"text":24,"correct":14},"D","投标截止日后28天","招标工程以投标截止日前28天，非招标工程以合同签订前28天为基准日，其后国家的法律法规、规章和政策发生变化引起工程造价增减变化的，发承包双方应当按照有关规定调整合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]