[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93081":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},93081,64,1,"单选题","依照《建设工程工程量清单计价规范》（GB 50500—2013）规定，包工包料工程的预付款支付比例不得低于签约合同价（扣除暂列金额）的______，不宜高于签约合同价（扣除暂列金额）的______。（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10%；20%",false,{"key":16,"text":17,"correct":14},"B","10%；25%",{"key":19,"text":20,"correct":21},"C","10%；30%",true,{"key":23,"text":24,"correct":14},"D","15%；30%","依照《建设工程工程量清单计价规范》（GB 50500—2013）规定，包工包料工程的预付款支付比例不得低于签约合同价（扣除暂列金额）的10%，不宜高于签约合同价（扣除暂列金额）的30%。预付款的总金额、分期拨付次数、每次付款金额、付款时间等，应根据工程规模、工期长短等具体情况，在合同中约定。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]