[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-93080":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},93080,64,1,"单选题","在合同履行期间，实际施工设计图纸与招标工程量清单某一项目的特征描述不符，且引起工程造价增加，应按照（ ）重新确定工程量清单项目的综合单价。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标文件中的项目特征",false,{"key":16,"text":17,"correct":18},"B","实际施工的项目特征",true,{"key":20,"text":21,"correct":14},"C","设计图纸",{"key":23,"text":24,"correct":14},"D","投标文件中的项目特征","对于项目特征描述不符时合同价款调整，合同履行期间，出现实际施工设计图纸（含设计变更）与招标工程量清单任一项目的特征描述不符，且该变化引起该项目的工程造价增减变化的，应按照实际施工的项目特征重新确定相应工程量清单项目的综合单价，计算调整的合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]